Architect |
Tongase & Patil Engineers (Regd). |
Project Management Consultant |
Tongase & Patil Engineers (Regd). |
Contractor |
Pawar Patkar Constructions Pvt Ltd |
Scope of work |
C.P. administative 1 no - 4740.00 sq.m Administrative (G + 3) |
Project Exp.Cost (Rs in lakh) |
846 |
Tendered Cost (Rs in lakh) |
591.87 |
Date of Completion of Project |
10/05/2012 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
24 |